CHANG3 PILATES

WEEK 1 – 9/11 to 15/11

 

Good morning team CHANG3,

A very quick turn around for the fitout to the pilates studio but exciting as the final piece of the puzzle will be in place so CHANG3 can open it’s doors for trade!!! 

Week 1 works complete.

Site set out and establishment

All Demo works completed

Electrical and data rough in

Framing to walls and ceiling.

Plaster board sheeting and setting.

Slab prep work complete

Co-ordination of additional works and quotes. Cat 1 air and fire / paint / glazing / plumbing etc.

This week the team will be aiming to complete the following tasks:

 

Painting to be complete

Installation of all joinery

Stone bench tops to be fit

Construction of the Salt Wall

Rendering and tiling to be complete 

Professional clean