HOTA

WEEK 2 – 14/12 to 20/12

Good Morning Team HOTA,

Another week down and all is tracking well on site.

Week 2 works complete.

– sprinkler fit off to grid
– a/c flexy and box install
– x 2pac ceiling panels installed
– remove and install new floor protection (base build water damage)
– receiving multiple deliveries for future on site work

 

 

This week the team will be aiming to complete the following tasks:

 

– Electrical works continued

– Commencement of Joinery instalation

– Stone Instal