MOTTO MOTTO ROBINA
Although this job has had some delays we are very excited to be back and unveiling another top class restaurant to the Gold Coast.!
The boys on site were able to have a full weeks work under their belt and met all scheduled timelines.
Works Completed in Week 1:
– Site set outs
– Plaster, framing 70% complete
– Plumbing 100 % complete
– Gas 100% roughed in
– Fire 80% roughed in
– A/C 80% roughed in
– Electrical 100% roughed in.
– Stainless hood install
– F.C sheeting to behind hood
– Structural for green ceiling feature install
This week the team will be aiming to complete the following tasks:
Monday
– Finish a/c rough in
– Finish fire rough in
– Plumbing inspection
– Plaster framing
Tuesday
– Plaster framing
Wednesday
– Plaster framing
– Structure in framing
Thursday
– Shopfront structural steel fit off
– Structure in framing
– Sheeting
Friday
– Sheeting
Saturday
– Sheeting
– Prep for setting