NIKE – INDOOROOPILLY

WEEK 1 – 28/9 to 4/10

Good Morning Matt,

Welcome to Zero 9’s Client Portal where we will keep you up to date with the ongoing works from the NIKE Indooroopilly site.

Exciting times as we started onsite last week. There were some last minute changes to the trade’s but Zero 9 were able to rip right in and get the ball rolling. Below is a list of what work that was able to be achieved.

Week 1 works complete.

Site set out and establishment

Electrical and data rough in

Framing to walls and ceiling.

Start of plaster board sheeting.

Co-ordination of additional works and quotes.

Cat 1 air and fire.

This week the team will be aiming to complete the following tasks:

 

Continued electrical and data rough in

Framing walls and shopfront work to continue

Glazing works to commence

Plasterboard sheeting and setting to continue