NIKE – INDOOROOPILLY
WEEK 2 – 5/10 to 11/10
Good Morning Matt,
With a full week behind us the team were able to get alot of work complete and are well on track with our schedule.
We have multiple tasks to be achieved this week to ensure that our timeframe is being met.
Week 1 works complete.
Electrical and data rough in
Framing to walls and shopfront
Plasterboard sheeting and setting
Commencement of Dura Brick cladding
Security rough in
Spray paint of ceiling
CAT 1 Fire works
This week the team will be aiming to complete the following tasks:
Continuation of plasterboard setting and painting
Shopfront works to continue
Glazing and Door measurements/mark ups
Checkpoint rough ins
Painting of Yshield to BOH wall