CHANG3 PILATES WEEK 2 – 16/11 to 21/11 Good morning team CHANG3, The finishing touches will be applied this week and you will be ready to roll come handover time on Wednesday. Week 2 works complete. Joinery instalation Render works to external walls and pillars...
CHANG3 PILATES WEEK 1 – 9/11 to 15/11 Good morning team CHANG3, A very quick turn around for the fitout to the pilates studio but exciting as the final piece of the puzzle will be in place so CHANG3 can open it’s doors for trade!!! Week 1 works complete....